This is a typical project schedule for a bathroom and separate  toilet renovation, tiled to the ceiling, with a new plaster ceiling and painting. Every renovation is slightly different, but this will give you a good idea of how the renovation will unfold.

  • Project begins
    • Strip out: 1 day
    • Rough in Plumbing: 1 day
    • Rough in Electrical: 1 day
    • Rebuild: 2 days
  • End week one
    • Waterproof: 2 days
    • Tile floors: 1 day
    • Tile to ceiling: up to 5 days (depending on tiles)
  • End week 2
    • Tile walls: 3 days
    • Order Shower screen: 10 days
    • Plaster ceiling: 2 days
  • End week 3
    • Paint ceiling: 1 day
    • Fit off electrical: 1 day
    • Fit off pc items: 1-2 day
    • Clean: 1 day
  • End of week 4